Transport Consultants in the UK

Browse 108 verified transport consultants across the UK. Get quotes for Transport Assessment, Travel Plan, Parking Survey and more.

108 verified transport consultants across the UK on The Planning Review.

What does a transport consultant do?

A transport consultant assesses the highways and transport implications of a proposed development and produces the technical evidence needed to satisfy the local highway authority. Transport is one of the most common reasons for planning objection and refusal, so their work is fundamental to securing consent for any scheme that generates significant traffic. The consultant determines whether a site can be safely accessed, models the wider traffic impact on the surrounding road network, and designs mitigation where necessary.

The scale of work depends on the size of the development. Smaller schemes may need only a Transport Statement, while larger proposals require a full Transport Assessment covering trip generation, junction capacity analysis, highway safety, parking, and sustainable transport measures. For developments above certain thresholds (typically 50 to 80 dwellings or significant commercial floorspace), a Framework Travel Plan is also required. The consultant uses industry-standard tools including TRICS (trip generation), TEMPRO (traffic growth factors), ARCADY (roundabout capacity), LINSIG (signalised junctions), and PICADY (priority junctions) to produce the evidence.

Beyond the technical assessment, transport consultants negotiate with the local highway authority (a statutory consultee on applications with transport implications), design site access arrangements and parking layouts to adoption standards, and agree Section 278 agreements for highway works and Section 106 transport contributions. Their ability to demonstrate that a development will not have a severe residual cumulative impact on the road network (the NPPF test at paragraph 115) is often the difference between consent and refusal.

When do you need a transport consultant?

  • The proposal is for 10 or more dwellings, which typically triggers a Transport Statement requirement
  • The development is 50 to 80+ dwellings or significant commercial floorspace, requiring a full Transport Assessment and Travel Plan
  • The scheme generates significant vehicle movements (generally more than 30 to 50 peak-hour trips)
  • A new or altered vehicular access onto the public highway is proposed and visibility splays must be demonstrated
  • The site has constrained highway access (narrow lanes, poor visibility, proximity to junctions, or width/weight restrictions)
  • The development is in an area with known traffic congestion where cumulative impact is a concern
  • The proposal includes reduced or no car parking and needs justification through accessibility analysis
  • The highway authority has raised a transport objection to a previous proposal or at pre-application stage
  • A Section 73 or variation application changes the transport implications of an existing consent
  • Transport evidence is needed for a planning appeal, including proof of evidence and expert witness testimony

Services you can get local quotes for

  • Construction Traffic Management Plan
  • Transport & Access

Frequently asked questions

How much does a Transport Assessment cost?

For a medium-sized residential development (50 to 150 dwellings), a Transport Assessment typically costs £8,000 to £20,000, including traffic surveys, junction modelling, and access design. A Transport Statement for a smaller scheme (10 to 50 dwellings) is less expensive, typically £3,000 to £8,000. Traffic surveys are often the largest single cost component: a set of manual classified counts at 3 to 4 junctions with automatic traffic counts on key links costs approximately £3,000 to £6,000. A Framework Travel Plan adds £2,000 to £5,000. A Stage 1 Road Safety Audit, if required, costs £1,500 to £3,000. For very large or contentious developments requiring extensive modelling (microsimulation, strategic model runs, or multiple junction assessments), transport consultancy fees can exceed £30,000 to £50,000+. Expert witness fees for planning appeals are typically £5,000 to £15,000 depending on the complexity and duration of the hearing or inquiry.

How long does the process take?

A Transport Assessment for a standard residential development takes 6 to 12 weeks from instruction to completion, assuming traffic surveys can be scheduled promptly. Traffic surveys should be conducted during neutral months (typically mid-January to mid-March, and mid-April to mid-July, and September to mid-November, avoiding school holidays and bank holidays), and survey slots with reputable survey companies may need to be booked 2 to 4 weeks in advance. Pre-application engagement with the highway authority, which is strongly recommended, adds 4 to 8 weeks to the overall programme but can prevent costly revisions later. Post-submission, responding to highway authority comments and negotiating Section 278/106 heads of terms can take a further 4 to 12 weeks depending on the complexity and the highway authority's responsiveness.

What is the NPPF "severe" test?

The NPPF states (paragraph 115) that development should only be prevented or refused on highways grounds if there would be an unacceptable impact on highway safety, or the residual cumulative impacts on the road network would be severe. This is a deliberately high bar. The word "severe" is not defined in the NPPF or PPG, and its interpretation has been the subject of numerous appeal decisions and court cases. In practice, it means that some increase in congestion and delay is acceptable, and a development should not be refused simply because it adds traffic to an already congested network. The impact must be demonstrably severe in the context of the existing conditions. Transport consultants use junction capacity modelling to demonstrate that the development's impact falls below this threshold, or to design mitigation that reduces the impact to an acceptable level.

What is a Section 278 agreement?

A Section 278 agreement (under the Highways Act 1980) is a legal agreement between a developer and the highway authority that allows the developer to carry out works on the public highway at the developer's expense. Common Section 278 works include new site access junctions, junction improvement works, new pedestrian crossings, bus stop improvements, footway and cycleway construction, and carriageway widening. The highway authority designs or approves the works to its adoption standards, and the developer funds the construction. The agreement includes a commuted sum for future maintenance. Section 278 works are typically secured by planning condition and must be completed before occupation of the development (or an agreed trigger point).

Can I build a car-free development?

Car-free or low-car developments are possible in locations with excellent public transport accessibility, typically in inner-city areas with high PTAL (Public Transport Accessibility Level) ratings. The transport consultant demonstrates through accessibility analysis that residents or occupiers can meet their travel needs without a private car, supported by a robust Travel Plan. Car-free developments typically provide car club spaces and extensive cycle parking instead of conventional car parking. However, many LPAs outside London remain cautious about reduced parking, and a poorly justified low-car scheme can lead to refusal or conditions requiring additional parking. The transport consultant's role is to present the evidence that the proposed parking level is appropriate for the location and that overspill parking on surrounding streets will not cause problems.

What is a Travel Plan and is it enforceable?

A Travel Plan is a package of practical measures aimed at reducing the proportion of journeys made by single-occupancy car and promoting sustainable alternatives. It is typically secured by a Section 106 agreement, which makes it legally binding on the developer and their successors. The Travel Plan includes targets (for example, reducing car mode share by a specified percentage within 5 years), monitoring arrangements (typically annual travel surveys), and remedial measures if targets are not met (which may include financial contributions to the highway authority for off-site transport improvements). A Travel Plan Coordinator must be appointed and funded for a specified period (typically 5 years post-occupation). Non-compliance with a Section 106 Travel Plan obligation is enforceable by the LPA.

Legal and regulatory framework

  • National Planning Policy Framework (NPPF), Chapter 9 — Promoting sustainable transport
  • Planning Practice Guidance (PPG) — Travel Plans, Transport Assessments and Statements
  • Highways Act 1980
  • Town and Country Planning (Development Management Procedure) (England) Order 2015
  • Manual for Streets (DfT, 2007) and Manual for Streets 2 (CIHT, 2010)
  • Design Manual for Roads and Bridges (DMRB)
  • Guidance on Transport Assessment (GTA) — DfT, 2007
  • CIHT Planning for Walking and Planning for Cycling guidance
  • Traffic Signs Regulations and General Directions (TSRGD) 2016

Professional accreditations

  • Chartered Institute of Logistics and Transport
  • Chartered Institution of Highways and Transportation
  • Institution of Civil Engineers
  • Royal Town Planning Institute

View all results on The Planning Review